    Question

    12 man can make a wall in 6 days. How many men required

    to complete the same work in 3 days ?
    A 23 Correct Answer Incorrect Answer
    B 24 Correct Answer Incorrect Answer
    C 20 Correct Answer Incorrect Answer
    D 21 Correct Answer Incorrect Answer

    Solution

    Given, M1 = 12 D1 = 6, M2 = ? and D2 = 3 From M1D1 = M2D2 тЗТ 12 x 6 = M2 x 3 тЗТ M2 = (12 x 6)/3 тИ┤ M2 = 24