Question
The ratio of time taken by P, Q and R to complete work
alone is 6:8:4 respectively. If all three together complete the work in 8 days, then find in how many days P alone will complete three-fourth of the same work? TYPE 47Solution
Ratio of efficiency of P, Q & R = 4 : 3 : 6 So, let total work = (4x + 3x + 6x) × 8 = 104x unit Required days = 104x × 3/4 × 1/4x = 19.5 days