Question
span >A and B together, B and C together and A and C together can complete a piece of work in 40 days, 30 days and 50 days respectively. Find the ratio of the efficiencies of A, B and C, respectively.
More Time and work Questions
- ‘A’ alone can do some work in 10 days. ‘B’ and ‘C’ together can do the same work in 4 days. If ‘B’ is half as efficient as ‘A’, then find the time taken by...
- A, B, and C together can complete a task in 8 days. A alone can do it in 24 days, and B alone can do it in 18 days. How long will it take C alone to finish...
- A certain number of men, represented as 'm', can finish a task in 40 days. However, if there were 15 additional men, the same task would be completed in 25...
- Team A can built a project in 6 hours less than the time taken by Team B to built the same project. The ratio of the strength of Team A to that of Team B ...
- 'P' and 'Q' together can complete the work in 12 days. 'Q' alone can complete the work in 20 days. If R is 25% more efficient than P, find the time taken b...
- A can finish a piece of work in 12 days, B in 15 days. They work together for 4 days, then A leaves and C joins B. C is 25% more efficient than B. In how m...
- ‘A’ alone can do some work in 20 days. ‘B’ and ‘C’ together can do the same work in 15 days. If ‘B’ is half as efficient as ‘A’, then find the time taken b...
- Neha and Seema can finish a work in 10 days and 25 days, respectively, when working alone. Neha started the work. After how many days should Seema join to ...
- "Arnav, Bhanu, and Chinu can finish a task in 18 days, 24 days, and 30 days, respectively. They all begin working together, but Bhanu stops after 4 days, a...
- A and B can do a work in 24 days and 32 days, respectively. If A works on it for ‘x’ days and B works on it for ‘x – 1’ days, then one-third of the work ge...