Question
Team A can built a project in 4 hours less than the time taken by Team B to built the same project. The ratio of the strength of Team A to that of Team B is ______. If it is given that the efficiencies of each member of both the teams is same (where the efficiency is measured in work done per hour), then which of the following ratios will satisfy the condition? (i) 5:3 (ii) 25:38 (iii) 15:11 (iv) 20:25
More Time and work Questions
- A can complete a job in 12 days, B in 18 days. They work together for 6 days, then A leaves. How many more days will B take to finish the remaining work?
- A can complete a work in 30 days. B takes 6 days less than A to complete the same work. In how many days can both of them together complete 60% of the work...
- X, Y and E can do piece of work in 24, 30 and 40 days respectively. All three began to work together but X and Y left 6 and 8 days respectively before comp...
- 138 unit of work can be completed by P alone in 23 days. P started working alone and joined by Q after 11 days such that they completed the remaining work ...
- 'Alex,' 'Ben,' and 'Charlie' can individually complete a task in 40, 60, and 100 days, respectively. They decide to work together, but there's a unique pat...
- A can complete a piece of work in 10 days , and B can complete the same work in 15 days . They start working together, and after some days A leaves. B co...
- A and B can complete a piece of work in 12 days and 15 days respectively. They start working together, but after 4 days, A leaves. In how many more days wi...
- A and B can complete a work together in 36 days. If A alone can complete one-third of the work in lsquo;xrsquo; days and remaining work is completed by B a...
- Rahul used to complete 25 problems in 50 minutes. But now, his efficiency has dropped by 20%. How much time will he need to complete the same number of pro...
- Akhil and Nikhil together can complete a work in 6 days while Nikhil alone takes 18 days to complete 60% of the work. If the efficiency of Sachin is 25% mo...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)