      Question

      P and Q individually can complete the work in 26 days

      and 39 days respectively. If the time taken by R alone to complete the work is 1.25 times the time taken by P and Q together to complete the work, find the time taken by R to complete the work while working alone.
      A 16.5 days Correct Answer Incorrect Answer
      B 19.5 days Correct Answer Incorrect Answer
      C 27 days Correct Answer Incorrect Answer
      D 28.5 days Correct Answer Incorrect Answer

      Solution

      Time taken by P and Q together to complete the work = (26 × 39)/ (26 + 39) = 15.6 days Time taken by R alone to complete the work = 1.25 × 15.6 = 19.5 days