Question
‘A’ and ‘B’ can do a piece of work in 10 days
and 20 days, respectively. They started working together but ‘A’ left after 3 days. Find the time taken by ‘B’ to complete the remaining work.Solution
Let total amount of work be 20 units (LCM of 10 and 20). Efficiency of ‘A’ = 20/10 = 2 units/day Efficiency of ‘B’ = 20/20 = 1 units/day Amount of work done by ‘A’ and ‘B’ together in 3 days = (2 + 1) × 3 = 9 units Time taken by B to complete remaining work = {(20 – 9)/1} = 11 days
Statement: Every year, at the beginning or at the end of the monsoons we have some cases of conjunctivitis but this year it seems to be a major epidemi...
Statement: While the workers laying cables underground in ABC locality, a main pipe supplying water to the houses burst and the locality was flooded....
Statement: The jurisdictional police has failed to arrest 26 convicts who are absconding after being released from prison on parole.
Courses of...
Statement : Cases of waterborne diseases have risen significantly in a city due to contaminated drinking water.
Courses of Action :
In the question below, few statements are given depicting an issue or a problem. You have to assume everything in the statements to be true even if th...
Statement:
School X which has hundreds of students, receiving regular complaints for the past few weeks that the food served in the student’s...
Project Lead 1: “Vendor PQR Solutions can deliver the software module quickly and at a lower cost.”
Project Lead 2: “Vendor LMN Tech off...
Statement : To enhance acoustic system and improve lighting, Australia’s world-renowned Opera House is to undergo its first major renovation since b...
The major road connecting the two main parts of the city is inundated due to heavy rains during past two days.
Courses of Action: (I)The govt. sh...
In the questions below, few statements are given depicting an issue or a problem. You have to assume everything in the statements to be true even if th...