πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    Question

    β€˜A’ and β€˜B’ can do a piece of work in 12 days

    and 20 days, respectively. They started working together but β€˜A’ left after 6 days. Find the time taken by β€˜B’ to complete the remaining work.
    A 4 days Correct Answer Incorrect Answer
    B 2 days Correct Answer Incorrect Answer
    C 5 days Correct Answer Incorrect Answer
    D 7 days Correct Answer Incorrect Answer

    Solution

    Let total amount of work be 60 units (LCM of 12 and 20). Efficiency of β€˜A’ = 60/12 = 5 units/day Efficiency of β€˜B’ = 60/20 = 3 units/day Amount of work done by β€˜A’ and β€˜B’ together in 6 days = (5 + 3) Γ— 6 = 48 units Time taken by B to complete remaining work = {(60 – 48)/3} = 4 days

    Practice Next

    Relevant for Exams:

    ask-question