πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      β€˜A’ and β€˜B’ can do a piece of work in 12 days

      and 20 days, respectively. They started working together but β€˜A’ left after 6 days. Find the time taken by β€˜B’ to complete the remaining work.
      A 4 days Correct Answer Incorrect Answer
      B 2 days Correct Answer Incorrect Answer
      C 5 days Correct Answer Incorrect Answer
      D 7 days Correct Answer Incorrect Answer

      Solution

      Let total amount of work be 60 units (LCM of 12 and 20). Efficiency of β€˜A’ = 60/12 = 5 units/day Efficiency of β€˜B’ = 60/20 = 3 units/day Amount of work done by β€˜A’ and β€˜B’ together in 6 days = (5 + 3) Γ— 6 = 48 units Time taken by B to complete remaining work = {(60 – 48)/3} = 4 days

      Practice Next

      Relevant for Exams:

      ask-question