Question
βAβ and βBβ can do a piece of work in 12 days
and 20 days, respectively. They started working together but βAβ left after 6 days. Find the time taken by βBβ to complete the remaining work.Solution
Let total amount of work be 60 units (LCM of 12 and 20). Efficiency of βAβ = 60/12 = 5 units/day Efficiency of βBβ = 60/20 = 3 units/day Amount of work done by βAβ and βBβ together in 6 days = (5 + 3) Γ 6 = 48 units Time taken by B to complete remaining work = {(60 β 48)/3} = 4 days
Select the alphanumeric term that will come next in the following series.
B7K, KB7, _______
Four letter-clusters have been given, out of which three are alike in some manner and one is different. Select the one that is different.
(Note: ...
Select the alphanumeric-cluster from among the given options that can replace the question mark (?) in the following series.
FY-7, IC-7, LG-9, OK...
Which of the following groups of letters when sequentially placed from left to right will complete the given series?Β
opq_stopqrsto_qrstopqrs_op...
Three Statements are given followed by two conclusions numbered I and II. Assuming the statements to be true, decide which of the conclusions logically ...
Three of the following four letter-clusters are alike in a certain way and one is different.
Pick the odd one out.
Select the figure that will replace the question mark (?) in the following figure series.
Read the given statements and conclusions carefully. Decide which of the given conclusions is/are true based on the given statements
Statements:...
Β A is taller than B but shorter than C. D is shorter than A but taller than B. Who is the tallest?
If β+β means βΓβ, βββ means βΓ·β, βΓβ means β+β, and βΓ·β means βββ, then what will be the value of the following ...