Question
‘A’ and ‘B’ can do a piece of work in 20 days and 25 days, respectively. They started working together but ‘A’ left after 4 days. Find the time taken by ‘B’ to complete the remaining work.
More Time and work Questions
- A person travelled for the first 150 km at a certain speed in 6 hours. After that, the speed of the person decreased by 6 km/h. If the person took a total ...
- P and Q individually can complete the work in 22 days and 33 days respectively. If the time taken by R alone to complete the work is 1.25 times the time ta...
- 132 unit of work can be completed by P alone in 22 days. P started working alone and joined by Q after 10 days such that they completed the remaining work ...
- Ashish and Anil can do a piece of work in 15 days and 20 days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the r...
- Vijay can do a piece of work in 10 days and Sanjay can do the same work in 15 days. If Vijay works for 4 days and got Rs. 1680, and the remaining work will...
- Sneha alone can type a report in 14 days, while Reena can do it in 21 days. If both work together and earn Rs. 14,700 for the job, how much will Reena get?
- 'Sita' can complete some work alone in 20 days. 'Geeta' is twice as efficient as 'Reeta' and three times as efficient as 'Sita'. If 'Sita' and 'Reeta' star...
- Ankit can complete a task in 16 days, while Bina alone can complete the same task in 24 days. Ankit starts the work alone and continues for 6 days. Then, B...
- Ram can finish a task alone in 45 days, whereas Ram and Rahul working together can complete the same task in 12 days. If Rahul works on the task alone for ...
- A can complete a job in 20 hours. B alone can complete the same job in 15 hrs. A work for 9 hrs and then the remaining job is completed by B. How many hour...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt