Question

In an office, an employee plans to do a work in 20 days with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops working for 6 hours a day. If he want to complete the work in the planned time with the laptops, how many hours per day the laptops have to work?

A 6 hours
B 12 hours
C 9 hours
D 10 hours
E None of these
Practice Next