Question
In an office, an employee plans to do a work in 20 days
with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops working for 6 hours a day. If he want to complete the work in the planned time with the laptops, how many hours per day the laptops have to work?Solution
Laptops do 40% of the work in 10 days, or 10 × 6 = 60 hours. So the rest of the (i.e., 60% of the work) can be done in, => (60 × 60)/40 = 90 hours This 90 hours of work has to be done in the remaining (20 – 10) = 10 days. Laptops have to work (90/10) = 9 hours a day to complete the work in the planned time.
Which feature allows you to rehearse the timing of a presentation?
_________ are the visual effects which appear in PowerPoint when one slide moves to next.
Which shortcut key is used to center-align text in Microsoft Word?
Which of the following file format can be added to a PowerPoint show?
Which of the following is not a file extension of an image file?
In MS Excel 365, which Microsoft Excel view allows you to see how the printed worksheet will look before actually printing it?
In Microsoft PowerPoint, which feature allows you to add visual effects between slides?
What is the address of the cell in an MS-Excel worksheet which lies at the intersection of the second row and the third column?
Which of the following is NOT a spreadsheet software?
Which of the following file extension denotes Microsoft Power Point Presentation