Question
In an office, an employee plans to do a work in 20 days
with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops working for 6 hours a day. If he want to complete the work in the planned time with the laptops, how many hours per day the laptops have to work?Solution
Laptops do 40% of the work in 10 days, or 10 × 6 = 60 hours. So the rest of the (i.e., 60% of the work) can be done in, => (60 × 60)/40 = 90 hours This 90 hours of work has to be done in the remaining (20 – 10) = 10 days. Laptops have to work (90/10) = 9 hours a day to complete the work in the planned time.
What is the total amount of aid package that the World Bank is set to approve for Sri Lanka, as mentioned in the information?
The voluntary amalgamation of New India Co-operative Bank Ltd. with Saraswat Co-operative Bank Ltd. will take effect on which date?
Which statement is correct about β INDUS X βΒ ? Β
a. INDUS X stands for India-United States Defence Acceleration Ecosyste .
b. The I...
- Which country promotes International Development Week (IDW)?
What is the theme of World Press Freedom Day 2025?
What is the name of the new domestically-built suicide drone developed by the Islamic Revolution Guards Corps (IRGC) Ground Force in Iran?
What was the value of net direct tax collection in Q1 of FY 2025β26?
The SDGs were set up in 2015 by the United Nations General Assembly and are intended to be achieved by ____________.
What was a significant factor in the UNESCO World Heritage Committee's decision to register Japan's Sado gold mine as a cultural heritage site?
Under which article of the Constitution is Census categorized as a Union subject, justifying caste enumeration in the national census?