Question
If Arjun can complete his work in 28 days by working 4
hours a day, how many hours a day should he work to finish the same work in 16 days?Solution
ATQ,
Let the efficiency of Arjun be 'x' units per hour
Therefore, total work = 4 × 28 × x = 112x units
Let the time he should work to complete the work in 16 days be 'y' hours a day.
ATQ;
112x = 16 × y × x
Or, y = 7
Therefore, he should work for 7 hours a day.
Alternate solution:
Required time = (4 × 28) ÷ 16 = 7 hours
Which of the following phase of National Dairy Plan was referred as ‘Mission Milk — The Next Revolution’, implemented by the National Dairy Develo...
In the context of five year plans, Which of the following can be regarded as basic objective of planning in India?
I. A sizeable increase in the ...
Which of the following horticulture development mission is subsumed in Mission for Integrated Development of Horticulture (MIDH)?
The market structure called monopoly exists where there _______ in any market.
Where in India the Cold Biosphere Desert located?
In a group of students, the number of girls is three-fourth of the number of boys. If two-third of the number of girls and one-half of the number of boy...
Which film won the Best Motion Picture – Drama award at the 2025 Golden Globe Awards?
Which one of the following is not the broker platform?
Which state has the second highest number of seats in the Lok Sabha?
According to Dalton’s atomic theory, atoms combine in the ratio of small whole numbers to form ______.