Question
If Arjun can complete his work in 28 days by working 4
hours a day, how many hours a day should he work to finish the same work in 16 days?Solution
ATQ,
Let the efficiency of Arjun be 'x' units per hour
Therefore, total work = 4 × 28 × x = 112x units
Let the time he should work to complete the work in 16 days be 'y' hours a day.
ATQ;
112x = 16 × y × x
Or, y = 7
Therefore, he should work for 7 hours a day.
Alternate solution:
Required time = (4 × 28) ÷ 16 = 7 hours
Irang, Maku and Tuival are important tributaries of:
An object is placed at the principal focus of a concave lens. Which of the following options represents the characteristics of the image formed?
EPFO is under the administrative control of which Ministry?
Which of the following statements is/are correct?
(1) Twelfth Schedule deals with the matters of Municipalities.
(2) 74th Constitutional...
Consider the following statements:
- The act of working at an extra job
- Mostly done in IT sector
- Swiggy ...
Select the set in which the numbers are related in the same way as are the numbers of the following sets.
(Note: Operations should be performed o...
Which layer of the OSI model is responsible for dividing data into smaller units for transmission?
When are strikes and lock-outs prohibited according to the Code on Wages Act 2020?
India State of Forest Report 2023 (ISFR) was recently released by which of the following:
In April 2023, the Election Commission abolished the national status of which of the following political parties?