If Arjun can complete his work in 28 days by working 4
hours a day, how many hours a day should he work to finish the same work in 16 days?Solution
ATQ,
Let the efficiency of Arjun be 'x' units per hour
Therefore, total work = 4 × 28 × x = 112x units
Let the time he should work to complete the work in 16 days be 'y' hours a day.
ATQ;
112x = 16 × y × x
Or, y = 7
Therefore, he should work for 7 hours a day.
Alternate solution:
Required time = (4 × 28) ÷ 16 = 7 hours
In a certain code language, ‘PREFER’ is coded as ‘KIVUVI’. What is the code for ‘DEFINE’ in that code language?
What is the code for ‘say may’ in the given code language?
What is the code for ‘letters newly’?
In a certain code language, ‘TRIPLE’ is written as ‘SUQJFM’, then how will ‘OPTION’ be written in that language?
If third digit of each number is replaced by 4, then how many numbers will be divisible by 7?
In a certain code language ‘SHINE’ is written as ‘ITIFO’ and ‘PRIVATE’ is written as ‘JSQVFUB’. How is &...
If ‘Earth’ is called as ‘Mars’, ‘Mars’ is called as ‘Venus’, and ‘Venus’ is called as ‘Jupiter’, then, which planet is known as...
In a certain code language, ‘KPURKTG’ is written as ‘LRVVLBH’. How will ‘HQTIKXG’ be written in that language?
In a certain code language, ‘market outlook remains’ is written as ‘xc, sd, kv’, ‘experts over positive remains’ is written as ‘kv, mn, qa...
If white is called blue, blue is called red, red is called yellow, yellow is called green, green is called black, black is called violet and violet is c...