Question
If Arjun can complete his work in 28 days by working 4
hours a day, how many hours a day should he work to finish the same work in 16 days?Solution
ATQ,
Let the efficiency of Arjun be 'x' units per hour
Therefore, total work = 4 × 28 × x = 112x units
Let the time he should work to complete the work in 16 days be 'y' hours a day.
ATQ;
112x = 16 × y × x
Or, y = 7
Therefore, he should work for 7 hours a day.
Alternate solution:
Required time = (4 × 28) ÷ 16 = 7 hours
- In each of the following questions, an idiomatic expression or a proverb has been given in bold . Choose the option that best expresses its meaning.
to hit the headlines
Select the most appropriate meaning of the given idiom.
full of beans
Once in a while
- In each question, five alternatives are given for the Idiom/Phrase given in bold in the sentence. Choose the alternative which best expresses the meaning o...
Select the most appropriate option to substitute the bold segment in the given sentence.Â
Because of his misbehaviour, he is bound to face the...
Directions : An idiom/phrase is given in bold. Following this idiom/phrase are given three sentences, which use the given idiom/phrase. The idiom/phra...
Fill in the blank given below using the correct idiom.
After studying all night, John managed to _______________ by completing his project and...
Choose the correct option showing the meaning of the Idiom highlighted in the given sentence
The boss told the employees to hit the ground run...
Select the option that best conveys the meaning of the bold idiom in the sentence.
Most of the political leaders have a gift of the gab, with whi...