Question
'A' is capable of completing a specific task on their
own in 20 days. 'B' can independently handle 60% of the same task in 18 days. If 'A' and 'B' collaborate on this task, how long will it take them to finish it completely?Solution
Time taken by 'A' to finish the entire work alone = 25 ÷ 1.25 = 20 days And time taken by 'B' to finish the entire work alone = 18 ÷ 0.6 = 30 days Let the total work be 60 units. {LCM (20 and 30)} So, efficiency of 'A' = 60 ÷ 20 = 3 units/day And efficiency of 'B' = 60 ÷ 30 = 2 units/day So, required time = {60/(3 + 2)} = 12 days
Which one of the following is not. the same as the other three ?
The widely used 7-bit ASCII code is employed:
To save an existing file with new name at a new location we should us _______ command.
Which type of computer security attack involves exploiting software vulnerabilities that have not been patched or updated?
URL stands for
Holding the mouse button down while moving an object or text is known as _________.
Non impact printer
Which one is the Open-source operating system?
What does a light pen contain?Â
Which of the following options is used to check spelling and grammar in a Microsoft Word document?