'A' is capable of completing a specific task on their own in 20 days. 'B' can independently handle 60% of the same task in 18 days. If 'A' and 'B' collaborate on this task, how long will it take them to finish it completely?

A 12 days
B 10 days
C 15 days
D 18 days
E 16 days