Question

    12 engineers complete designing 180 blueprints in 15

    days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?
    A 18 Correct Answer Incorrect Answer
    B 9 Correct Answer Incorrect Answer
    C 13 Correct Answer Incorrect Answer
    D 15 Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ,

    Let the required number of engineers be ‘w’ and let efficiency of each engineer be ‘M’ units per day

    (12 × 15 × M) ÷ 180 = (18 × w × M) ÷ 270

    So, w = 15