📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    âš¡ Azaadi sale - Celebrate Independence Day with Flat 55% Off On all courses! 13 to 17 Aug âš¡ Enroll Now

    Question

    12 engineers complete designing 180 blueprints in 15

    days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?
    A 18 Correct Answer Incorrect Answer
    B 9 Correct Answer Incorrect Answer
    C 13 Correct Answer Incorrect Answer
    D 15 Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ,

    Let the required number of engineers be ‘w’ and let efficiency of each engineer be ‘M’ units per day

    (12 × 15 × M) ÷ 180 = (18 × w × M) ÷ 270

    So, w = 15

    Practice Next
    More Time and work Questions

    Relevant for Exams:

    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call