Question
12 engineers complete designing 180 blueprints in 15
days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?Solution
ATQ,
Let the required number of engineers be ‘w’ and let efficiency of each engineer be ‘M’ units per day
(12 × 15 × M) ÷ 180 = (18 × w × M) ÷ 270
So, w = 15
Jack is twice efficient as Jill and Jill can do a piece of work in 30 days. Jill started the work and after a few days Jack joined him. They completed t...
- A team of 6 workers, each working 8 hours per day, can build a 200-metre-long wall in 15 days. How many workers would be needed to construct a 300-metre-lo...
 Saurabh can complete a piece of work in 20 days. He worked for 5 days and left. Anirudh completed the remaining work in 12 days. If both had done the ...
P and Q can complete a work in 28 days and 42 days, respectively. P, Q and R together can complete the work in 14 days. If R get a total wage of Rs. 546...
A can complete a work in 15 days. B takes 6 days less than A to complete the same work. In how many days can both of them together complete 80% of the w...
- Varun and Arnav can finish a work in 28 days and 56 days respectively when working alone. Varun starts first. In how many days should Arnav join him so tha...
A and B together can complete a work in 15 days, while B and C together can complete the same work in 20 days. If A, B, and C together can complete the ...
Ajay and Vijay together can paint a piece of furniture in 11 days. Vijay and Chirag together, as well as Ajay and Chirag together...
A takes 24 hours more than B to complete the work, and 32 hours more than C to complete the same work. The combined time taken by A and B to finish the ...
- 'X' can complete 75% of a work in 15 days, whereas 'Y' can complete 25% of the same work in 10 days. They both started working together, but 'Y' left the j...