Question
12 engineers complete designing 180 blueprints in 15
days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?Solution
ATQ,
Let the required number of engineers be ‘w’ and let efficiency of each engineer be ‘M’ units per day
(12 × 15 × M) ÷ 180 = (18 × w × M) ÷ 270
So, w = 15
Simplify the following expression and find the final value:
(18 ÷ 6 of 2 + 7 of 5) ÷ 5
(1520 - 1350) ÷ (550 – 500) = ?
Simplify the following expressions and choose the correct option.
[540 ÷ (6 × 3) + 7.5 × 4] ÷ 3 = ?
(64/25)? × (125/512)?-1 = 5/8
52% of 400 + √(?) = 60% of 600 - 25% of 400
What will come in the place of question mark (?) in the given expression?
(72 × 4 – 92) ÷ 14 = ?
32% of 450 + 60% of 150 = ? × 9

82.3 × 644.7 × 723.4 × 815.85 = 72?
961 × 4 ÷ 31 – 15% of 180 = ? – 73