Question
A, B, C can do a piece of work in 11 days, 20 days, and
22 days respectively. If B works daily and is supported by A and C on alternate days beginning with A, then in how many days will the work be finished?Solution
ABC 112022 220 201110 working fashion = (A +B, C + B) 2 days = 31 + 21 = 52 units 8 days = 208 units Remaining work =220-208=12unit 9 days = 12/31 => 220units Total time =8+(12/31) days=8 +(12/31 days
The âNutrient Indexâ concept in soil fertility assessment was introduced by:
The Phenomenon of inheritance of linked genes in same linkage group is called as
Which of the following statement is not correct about the facilitated diffusion?Â
Water movement under unsaturated soil conditions is mainly driven by_____
Which insect lays eggs in guava fruits, causing damage and rendering them unmarketable?
In furrow irrigation, which factor mainly influences the uniform distribution of water?
Karonda is a rich source of
The process of loss of water from plant is
Why are insects considered among the most successful organisms on Earth in terms of survival and proliferation across ecosystems?
In which part of India the shifting cultivation, locally known âJhumingâ is widely practiced?Â