Question
25 men can complete a piece of work in 13 days. One man
starts the work and after every day one more man joins the work and this continues till the work is completed. Then, in how many days will the work be completed?Solution
Let 1 day work of 1 man = 1 units So total work = 25 ×13 = 325 units Suppose after n days work is finished. So, 1 + 2 + ………… +n = 325 ⇒ (n(n+1))/2 = 325 n² + n – 650 = 0 n² + 26n – 25n – 650 = 0 n(n + 26 ) – 25(n + 26) = 0 (n - 25)  (n + 26) ∴ n = 25 Hence, the work will be finished in 25 days.
Statements:
Some P are Q
All Q are R
Some R are S
Conclusions:
I. Some R are not P
II. All R are P
In the question below there are three statements followed by three conclusions I, II and III. You have to take the four given statements to be true eve...
What is the shortest distance between S and U?
- In the question below some statements are given followed by three conclusions I, II and III. You have to take the given statements to be true even if they ...
Statement:
Some pens are pencils
Only a few pencils are tables
All tables are notebooks
Conclusion:
I. All pens can b...
- Read the given statements and conclusions carefully. Assuming that the information given in the statements is true, even if it app ear s to be at variance ...
Two statements are given followed by two conclusions numbered I& II. Assuming the statements to be true, even if they seem to be at variance with commo...
In the question below there are three statements followed by two conclusions I and II. You have to take the three given statements to be true even if t...
In the question below some statements are given followed by two conclusions I and II. You have to take the given statements to be true even if they see...
Statements : All roses are Daisy.
No Lilly is a rose.
No Daisy is a Tulip.
Conclusions : I . Â No Tulip is a Daisy.
<...