Question

Raman can complete a certain task by himself in 30 days. Both Raman and Rajat worked together to finish this task, earning a combined wage of Rs. 5,850. Out of this, Rajat received Rs. 2,250 as his share of the wage. Calculate how long it would take for Rajat to complete the same task on his own.

A 56 days
B 72 days
C 48 days
D 54 days
E 40 days