Question
Anand and Manav can collaboratively finish a task in
{40/3} days, while Anand alone requires 24 days to complete the same task. Given that Prachi's efficiency is 25% lower than Manav's, determine the number of days it will take Prachi to complete the work on her own.Solution
Let the total work be 120 units (LCM of (40/3) and 24) . Combined efficiency of Anand and Manav together = 120 Γ· (40/3) = 9 units/day Efficiency of Anand = (120/24) = 5 units/day So, efficiency of Manav = 9 - 5 = 4 units/day Efficiency of Prachi = 0.75 X 4 = 3 units/day Required time taken = (120/3) = 40 days
P can do a piece of work in 15 days, Q can complete double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, ...
- Alex and Ben can complete a job individually in 14 days and 21 days, respectively. If they take turns to work one day each, beginning with Alex, how long w...
βXβ and βYβ can do a task together in 15 days. If βXβ alone takes 25 days to complete it, then how much time will βYβ take to finish the...
βPβ and βQβ can complete a task together in 24 days. If βPβ alone can do it in 40 days, find the number of days βQβ alone will take to f...
A can complete a work in 40 days. B takes 20 days less than A to complete the same work. In how many days can both of them together complete 90% of the ...
P can do a piece of work in 30 days. Q do the same work in 40 days. R can do it in 35 days. P and R worked for 4 days and handed it to Q. Q worked for s...
X can do a piece of work in 15 days. He worked at it for 3 days and then Y finished it in 16 days. In how many days can X and Y together finish the work?
A job is done by 15 men in 30 days and 30 women in 20 days. How many days will it take for 8 men and 12 women to finish the work?
P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 ...
12 engineers complete designing 180 blueprints in 15 days. If the goal is to complete 270 blueprints in 18 days, how many engineers are required?