Question
Some Category of workers can complete a decided project
in 20 days. However, due to some unpredicted situation, 5 workers were absent. That’s why, the project got detained by 5 days. If each worker does the similar amount of work and all workers are equally efficient, then how many workers were initially allocated to the project?Solution
Let's we consider that the number of workers initially allocated to the project is 'a'. In one day, 'a' workers can complete 1/20th of the project. Then, due to unpredicted situation there will absence of 5 workers, the effective number of workers working on the project is (a - 5). Since the project got detained by 5 days, the entire number of days taken to complete the project is 20 + 5 = 25. Therefore, we can set up the equation to solve for 'a': (a- 5) x 25 = a x 20 25a - 125 = 20a 25a – 20a = 125 5a = 125 a = 125 / 5 a = 25 Therefore, the initial number of workers allocated to the project is 25.
Which of the following assessee is not liable to pay advance tax u/s 207?
In insurance accounting, what is "unearned premium"?
Calculate the inventory turnover ratio:
Which of the following can lead to multiple IRRs?
Goods costing ₹ 60,000 sold to Manish at a profit of 25% on sales less Trade Discount @ 5%.
Calculate the amount to be shown in Sales Account:
Withdrawal column of the Pass Book showed a wrong entry of Rs. 112. When the balance as per Cash Book is the starting point.
Â
What should be the correct Journal Entry for booking premium income in case of Incoming coinsurance:
Which method of depreciation results in higher depreciation in earlier years?
Which of these is a liability arising from construction contracts under percentage-of-completion where billings exceed progress?
If the labour efficiency variance is unfavorabie but the labour rate variance is favourable, which of the following could be a reason?