Question
Q can complete a project in ‘x ‘ hours , R needs
‘0.7x’ hours to do half of The same project. R and S jointly can complete the same project in 1/3 of time taken by Q to complete the work alone. Q takes 90 hours more to complete alone as compared to time taken by all three jointly to complete the work. Find the time taken by S to complete 80% of the project alone?ÂSolution
Let time taken by R to finish work is – x hr, By Q is = 1.4x hr Therefore, R+S = (1.4x/3)hr So, by S alone work = [1/3/1.4x) – 1/x ] = 7x/8 hr Entire time taken by all together = (1.4x - 90)hr Therefore, 1/x + 1/1.4x + 8/7x = 1/1.4x-90 1.4x +1+1.6x/1.4x = 1/1.4x -90 5.6x -360 = 1.4x x = 600/7 Hence, time taken by S alone to complete 80% = 7/8 x 600/7 x 0.8 = 60 hrs
24, 42, 60, ?, 96, 114
What will come in place of (?) question mark in the given number series.
10, 17, 26, 37, 50, ?
660, 653, 639, 618, 590, ?
What will come in place of the question mark (?) in the following series?
75, 219, 388, ?, 809, 1065168, 178, ?, 273, 400, 618, 963
60   61    57   66    ?      75    39
...What will come in place of the question mark (?) in the following series?
2, 5, 14, 41, 122, 365, ?
81, 83, 87, 95, 111, ?
What will come in place of the question mark (?) in the following series?
400, 841, 1202, ?, 1716, 1885
64, 66, 69, 74, 81, ?