Question
P and Q can complete a piece of work individually in 12
days and 20 days, respectively. They start working together, but after 6 days, Q leaves the work. P continues and completes the remaining work alone. How many total days did it take to finish the entire work?Solution
Let total work = 60 units (LCM of 12 and 20)
Efficiency of 'P' = (60/12) = 5 units/day
Efficiency of 'Q' = (60/20) = 3 units/day
Amount of work completed by 'P' and 'Q' together in 6 days = 6 X (5 + 3) = 48 units
Remaining work = 60 - 48 = 12 units
Time taken by 'P' to complete the remaining work = (12/5) = 2.4 days
Required time taken = 6 + 2.4 = 8.4 days
Statements: O < N = M < L, Q < P ≥ M ≤ R
Conclusion:
I. R > O
II. Q ≤ LÂ
Select the related number from the given alternatives:
653:87:: 8327: ____
If 12 # 34 = 14 and 67 # 88 = 106, then 45 # 67 = ?
In the following question, select the related number from the given alternatives.
68 : 70 :: 45: ?
Select the option that is related to the third number in the same way as the second number is related to first number and the sixth number is related t...
Select the option that is related to third number-cluster in the same way first number cluster is related to second number-cluster.
94: 97 ...Select the combination of letters that when sequentially placed in the blanks of the given letter series will complete the series.
 _ _ N _ P _...
Select the option that is related to the sixth number in the same way as the first number is related to the second number and the third number is relate...
- Select the option that is related to the third number in the same way as the second number is related to first number and the sixth number is related to th...
Theatre : Actor :: Field : ?