Start learning 50% faster. Sign in now
Let total work = 60 units (LCM of 12 and 20)
Efficiency of 'P' = (60/12) = 5 units/day
Efficiency of 'Q' = (60/20) = 3 units/day
Amount of work completed by 'P' and 'Q' together in 6 days = 6 X (5 + 3) = 48 units
Remaining work = 60 - 48 = 12 units
Time taken by 'P' to complete the remaining work = (12/5) = 2.4 days
Required time taken = 6 + 2.4 = 8.4 days
2, 6, 24, 96, 384, 1536, 6144
556, 547, 483, 458, 242, 196
Find the wrong number in the given number series.
33, 42, 78, 159, 317, 528
Find the wrong term in the given series below.
2847, 2954, 2799, 3088, 2727, 3256
384, 1152, 144, 432, 56, 162
5000, 4050, 3240, 2268, 1360.8, 680.4
2.5, 15, 81, 325, 976, 1953
Direction: Find the wrong number in given number series.
1977, 1945, 1837, 1575, 1081, 217.
1, 1, 3, 15, 105, 942