Question
P and Q can complete a piece of work individually in 12
days and 20 days, respectively. They start working together, but after 6 days, Q leaves the work. P continues and completes the remaining work alone. How many total days did it take to finish the entire work?Solution
Let total work = 60 units (LCM of 12 and 20)
Efficiency of 'P' = (60/12) = 5 units/day
Efficiency of 'Q' = (60/20) = 3 units/day
Amount of work completed by 'P' and 'Q' together in 6 days = 6 X (5 + 3) = 48 units
Remaining work = 60 - 48 = 12 units
Time taken by 'P' to complete the remaining work = (12/5) = 2.4 days
Required time taken = 6 + 2.4 = 8.4 days
When any person has reason to believe that he may be arrested on an accusation of having committed a non bailable offence he may apply for anticipatory...
The Central Vigilance Commission is classified as a:Â
Consider the following statements regarding adjudicating officers under the IT Act, 2000:
1. They are appointed by the Central Government.
The assessment of land revenue on any land shall be made with reference to the use of land.
When is a principal required to compensate their agent under the Special Contract Act?
Under the Occupational Safety, Health and Working Conditions Code, how many days in a week can a worker typically be allowed to work in an establishment?
Section 17(1) proviso of the Environment (Protection) Act, 1986 provides defense to Head if he proves offence committed:
When consent to an agreement is caused by coercion, fraud or misrepresentation, the agreement is a contract :Â
After retirement, a Judge of a High Court can undertake practice in-
Under Section 37(1) of the BNS, 2023, which of the following acts does NOT allow the exercise of the right of private defence?Â