Aβ and βBβ together can complete a work in 15 days
while βAβ takes 20 days to complete the same work alone. If βCβ is 50% more efficient than βBβ, then find the time taken by βCβ alone to complete the whole work.Solution
Let the total work = 60 units Efficiency of (A + B) = 60/15 = 4 units/day Efficiency of βAβ = 60/20 = 3 units/day Therefore, efficiency of βBβ = 4 β 3 = 1 unit/day Efficiency of βCβ = 1.5 Γ 1 = 1.5 units/day Required time taken = 60/1.5 = 40 days
How were the Indian textile industries affected by the industrial revolution in Britain?
The language of the Aryan texts was:
Amarkantaka is the origin of which river?
Consider the following statements:
A) Judicial decisions are bound by precedent in common law, whereas quasi-judicial decisions are generally not...
What is the budget package allocated in 2022-23 for the PM Kisan scheme?
Which one out of the following states has a coastline?
Mohi Bahauddin Dagar, a renowned musician, is known for playing which of the following instruments?
Who among the following singers has been awarded with Bharat Ratna?
In June 2020, the Central government approved an Ordinance to bring all urban and multi-state cooperative banks under the direct supervision of RBI. In...
Who is the author of the book 'The Best Thing About You is You'?