Let the total work = 60 units Efficiency of (A + B) = 60/15 = 4 units/day Efficiency of ‘A’ = 60/20 = 3 units/day Therefore, efficiency of ‘B’ = 4 – 3 = 1 unit/day Efficiency of ‘C’ = 1.5 × 1 = 1.5 units/day Required time taken = 60/1.5 = 40 days