Question
A’ and ‘B’ together can complete a work in 15 days
while ‘A’ takes 20 days to complete the same work alone. If ‘C’ is 50% more efficient than ‘B’, then find the time taken by ‘C’ alone to complete the whole work.Solution
Let the total work = 60 units Efficiency of (A + B) = 60/15 = 4 units/day Efficiency of ‘A’ = 60/20 = 3 units/day Therefore, efficiency of ‘B’ = 4 – 3 = 1 unit/day Efficiency of ‘C’ = 1.5 × 1 = 1.5 units/day Required time taken = 60/1.5 = 40 days
Which of the following integrity constraints ensures that every non-null foreign key value must reference an existing primary key value in another tabl...
Hashing is used for:
The amortized cost of appending an element at the end of a dynamic array is:
Consider the following stack operations. What will be the content of the stack after executing all the operations?
Stackstack = new Stack... Which of the following is NOT among the OWASP Top 10 Web Security Risks?
In Python, what will be the output of the following code snippet, considering scope rules?
x = 5
In asymmetric encryption, which of the following statements is correct?
Which algorithm constructs a suffix tree in linear time?
What is the primary purpose of a B+ Tree in a database management system?
Which sorting algorithm has O(n log n) average case?