πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      Amit can do certain work alone in 'w' days. Arjit can do

      the same work alone in (w + 12) days.Gaurav started working and did (1/2) the work at the efficiency of Amit and rest work at efficiency of Arjit, and finished the work in 24 days. Then, find the value of (w2 + 5w -40)
      A 450 Correct Answer Incorrect Answer
      B 650 Correct Answer Incorrect Answer
      C 370 Correct Answer Incorrect Answer
      D 374 Correct Answer Incorrect Answer
      E none of these Correct Answer Incorrect Answer

      Solution

      ATQ, we can say that Since 'Gaurav' completed (1/2) of the work with (1/2) the efficiency of 'Amit'.Β  So, time taken by him to complete (1/2) of the work = (w/2) days Similarly, time taken by 'Gaurav' to complete other (1/2) of the work =Β  [(w + 12)/2] days So, (w/2) + {(w + 12)/2} = 24 Or, w + 6 = 24 Or, w = 18 So, w2 + 5w - 40 = 324 + 90 - 40 =Β  324 + 50 = 374

      Practice Next
      ask-question