Question

‘P’ can complete 40% of a task in 24 days, while ‘Q’ can complete 25% of the task in 20 days. How long will it take approximately for ‘P’ and ‘Q’ together to finish 75% of the entire work?

A 10.5 days
B 25.7 days
C 45.02 days
D None of these