Question
A can do a work in 10 days and B in 15 days. If they
work on it together for 4 days then in how many days the remaining work will be completed by B?Solution
Total work = Number of days × 1 day’s work (efficiency) Total work = LCM (10, 15) = 30 unit 1 day’s work of A = 30/10 = 3 unit 1 day’s work of B = 30/15 = 2 unit 1 day’s work of (A + B) = 3 + 2 = 5 unit Now, 4 day’s work of (A + B) together = 4 × 5 = 20 unit Remaining work = 30 – 20 = 10 Remaining work completed by B = 10/2 = 5 days