Question
A does 55% of some work in 12 days. Later, with B’s
help, she completes the remaining work in 4 days. In how many days can Be B complete the entire work alone? type-sscSolution
Let total work = 120 units A does 45% of the work=120×45/100=36 Since A does 45% of the work (i.e. 36 units) in 12 days, A = 36/12 = 3 units per day Work left = 120 − 36 = 84 units Let B do x units of work per day. B and A finish the pending work in 4 days. ∴ 4(x + 3) = 84 ∴ 4x = 84 − 12 = 72 i.e. x = 18 units ∴ Time taken by B to complete the work = 120/18 = 6+2/3
days
Two different alloys contain steel and aluminum in the ratios of 11:4 and 2:13, respectively. In what proportion should these two alloys be combined to ...
The sum to n terms of the series 1 + 1 + 3 + 1 + 3 + 5 + 1 + 3 + 5 + 7 …………………… is
If a, b, c are in geometric progression and a + b + c = 14, a² + b² + c² = 84, find a, b, c.
The current age of Anupama is 25% greater than Chinky's age. Four years ago, the ages of Beena and Chinky were in the ratio of 4:...
3600, 600, 120, 30, 10, ?
The first odd number is 1, second is 3, third is 5 and fourth is 7 and so on, then find the 188th odd number?
If the median and mode of a data set are 6 and 12 respectively, then find the mean of the data.
What is least number which when successively divided by 6, 4 and 4 leaves a remainder 5, 3 and 3 respectively?
The sum of total surface area of two cubes is 1248-centimeter square. If the product of the length of their edges is 96 centimeter square. Find the diff...
Pipe ‘A’ and pipe ‘B’ can fill a cistern in 20 minutes and 15 minutes respectively. Pipe ‘C’ alone can empty the cistern in 12 minutes. If a...