Question
A does 55% of some work in 12 days. Later, with B’s
help, she completes the remaining work in 4 days. In how many days can Be B complete the entire work alone? type-sscSolution
Let total work = 120 units A does 45% of the work=120×45/100=36 Since A does 45% of the work (i.e. 36 units) in 12 days, A = 36/12 = 3 units per day Work left = 120 − 36 = 84 units Let B do x units of work per day. B and A finish the pending work in 4 days. ∴ 4(x + 3) = 84 ∴ 4x = 84 − 12 = 72 i.e. x = 18 units ∴ Time taken by B to complete the work = 120/18 = 6+2/3
days
Coal India Limited (CIL) recently signed an MoU to establish a Centre of Clean Coal Energy and Net Zero (CLEANZ) with which institution?
Which layer of the earth's atmosphere contains the ozone layer?
Who among the following was involved in the Alipore Bomb Case?
Which of the following statements is correct?
Which fintech giant launched the consumer-facing application Pincode integrated into India's Open Network for Digital Commerce (ONDC) framework?
What was the rank of India in the medal tally at the 14th International Olympiad on Astronomy and Astrophysics (IOAA) 2021, organized by Colombia in Nov...
What is the pattern of the New Education Policy (NEP) 2020 in India?
The perimeter of a square is equal to the perimeter of a rectangle of length 56 cm and breadth 42 cm. Find the perimeter of a semicircle (in cm) whose d...
The sum of length, breadth and height of cuboid is 20cm.If the length of the diagonal is 12 cm, then find the total surface area of the cuboid( in cm
Palladium on barium sulphate (Pd/BaSOâ‚„) is also known as: