📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    âš¡ Azaadi sale - Celebrate Independence Day with Flat 55% Off On all courses! 13 to 17 Aug âš¡ Enroll Now

    Question

    A does 55% of some work in 12 days. Later, with B’s

    help, she completes the remaining work in 4 days. In how many days can Be B complete the entire work alone? type-ssc
    A 4 Correct Answer Incorrect Answer
    B 1 Correct Answer Incorrect Answer
    C 2 Correct Answer Incorrect Answer
    D 3 Correct Answer Incorrect Answer

    Solution

    Let total work = 120 units A does 45% of the work=120×45/100=36 Since A does 45% of the work (i.e. 36 units) in 12 days, A = 36/12 = 3 units per day Work left = 120 − 36 = 84 units Let B do x units of work per day. B and A finish the pending work in 4 days. ∴ 4(x + 3) = 84 ∴ 4x = 84 − 12 = 72 i.e. x = 18 units ∴ Time taken by B to complete the work = 120/18 = 6+2/3 days

    Practice Next

    Relevant for Exams:

    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call