Question
A does 55% of some work in 12 days. Later, with B’s
help, she completes the remaining work in 4 days. In how many days can Be B complete the entire work alone? type-sscSolution
Let total work = 120 units A does 45% of the work=120×45/100=36 Since A does 45% of the work (i.e. 36 units) in 12 days, A = 36/12 = 3 units per day Work left = 120 − 36 = 84 units Let B do x units of work per day. B and A finish the pending work in 4 days. ∴ 4(x + 3) = 84 ∴ 4x = 84 − 12 = 72 i.e. x = 18 units ∴ Time taken by B to complete the work = 120/18 = 6+2/3
days
In the days before the advent of television, the radio brought the family together to listen news, music and drama.
The photocopier is on the blink again.
The chief executive of DWS, one of Europe’s biggest asset managers, (A)/has launch a staunch defence of quarterly reporting, (B)/ just weeks after US ...
Among the challenges facing the Indian Economy,/ RBI governor stressed the importance of/ sentiment and mood which he said is / not sufficiently posi...
Global commodities have witnessed a bull run over the last 12 months, revival hopes of the beginning of the next super cycle in commodity prices.
...Given below is a sentence with or without an error. The error, if any, is in one part of the sentence. Choose the correct part which contains the error...
It is aimed at sensitising and inspiring (1)/the younger generation about (2)/the leadership, vision and achievements (3)/of all our prime minister (4).
The midnight session in Parliament that marked India’s transition to Goods and Services Tax was reminiscent of a similar occasion on the eve of In...
Nazi war criminals accused with (A)/participating in the Holocaust continue (B)/to stand trial and any attempt (C)/of denial is met with punishment (D).
The need for reforming the country’s murky electoral processes again attracted the attention for the Court when it struck down a provision in the elec...