Question
Raju, Shubham, and Mohan can work for 15 days, 20 days
and 25 days respectively. In how many days will the work be finished if they do it on alternate days?Solution
   RajSubhamMohan 152025 LCM-300 201512 Working type- Raj, Subham, Mohan, Raj, Shubham, Mohan…. Working in first 3days =20+15+12 =47units 3×6days =47×6=282units 18days =282units 19days =18/20=9/10days Total days = 18+9/10=189/10days
Which of the following publishes the World Investment Report?
In which of the following phases of change does the organisations require support to sustain the change?
W Ltd. issued 8,000 shares of Rs.10 each at per. Amount called up Rs.4 on application, Rs.3 on allotment and Rs.3 on first and final call. Mr. R, a shar...
What is moratorium period for small and startup firms under Insolvency and Bankruptcy Code 2016?
What is a Follow-on Public Offer (FPO)?
Improving the employee performance is a key part of human resource development. Which of the following helps in achieving this by increasing employee’...
What is the maximum amount of loan an individual borrower can get from Tier-2 to 4 UCBs for housing loans?
Which of the following is nonverbal communication?
The Economic Survey 2023 projects a baseline GDP growth of ________ in real terms in FY24.
Which among the following method is also called as Original cost method, Fixed Installment method or Equal Installment method?