Question

P and Q agreed to complete a task for Rs. 6600. P can finish the work alone in 12 days, and Q can complete it alone in 10 days. If they work together, what will be the difference in the amounts they receive for the work?

A Rs. 500
B Rs. 600
C Rs. 350
D Rs. 420