Question
Aman can complete a task in 24 days, while Bhavna can
finish the same task in 40 days. How long will it take for Chetan to finish the task if his efficiency is 25% more than the combined efficiency of Aman and Bhavna?Solution
Let total amount of work = 120 units (LCM of 24 and 40) Work done by Aman in one day = 120 / 24 = 5 units Work done by Bhavna in one day = 120 / 40 = 3 units Combined = 5 + 3 = 8 units Chetan’s efficiency = 1.25 × 8 = 10 units/day Time taken by Chetan = 120 / 10 = 12 days
'k' is the value that should be subtracted from (7/8) in order to get (1/4). What will be the remainder when denominator of 'k' is divided by its numera...
A number 'N' when divided by 14 leaves 7 as remainder. If 5N² is divided by 14, then find the remainder.
Find the least number greater than 100 which leaves a remainder of 4 when divided by 5, 6, and 7.
Find the smallest 3-digit number which is exactly divisible by 7.
Sum of three positive numbers is 128. If the ratio of the first and second number is 7:9, respectively while difference between the first and third numb...
If a number 'a' is divisible by 18 and another number 'b' is divisible by 12, then (a2 – b2) is divisible by:
Range of the given data 23,19,16,17,21,9,18,6.
Some toys were distributed among (x + 2) students such that each student received 8 toys. If there had been 6 students more, then toys received by each ...
How many whole numbers from 1 to 500 (both included) are divisible by 3 or 5?
If the 6-digit number '5a1897' is divisible by '11', determine the value of 'a'.