Question
‘Neha’ can complete a task in 90 days. She worked for 54 days and then left. The rest of the task was completed by ‘Karan’ in 24 days. How much time would Karan take to finish 80% of the task?
More Time and work Questions
- ‘P’ can complete 40% of a task in 24 days, while ‘Q’ can complete 25% of the task in 20 days. How long will it take approximately for ‘P’ and ‘Q’ together ...
- Worker ‘P’ can complete a job in 30 days, and together with ‘Q’, they can finish it in 12 days. If ‘Q’ worked alone for 15 days and then stopped, how long ...
- 'Preeti' can complete a piece of work in 70 days, while 'Bhanumati' can complete it in 90 days. They both started the work together, but 'Preeti' left afte...
- A painter charges ₹500 for every hour of work. If he works for 6 hours a day and completes a project in 5 days, what is the total amount charged by the pai...
- Karan, Arjun and Krunal alone can complete a work in 35, 70 and 60 days respectively. All of them started working together but after 3 days from start Kara...
- A and B can complete a task together in 24 days, while B alone takes 48 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- A boy(labour) was appointed by a manager on the term that he would be paid Rs 55 for each day of his work but would be fined at the rate of Rs 5 per day fo...
- Varun and Arnav can finish a work in 28 days and 56 days respectively when working alone. Varun starts first. In how many days should Arnav join him so tha...
- 180 unit of work can be completed by P alone in 30 days. P started working alone and joined by Q after 18 days such that they completed the remaining work ...
- A can complete a work in 15 days. B takes 6 days less than A to complete the same work. In how many days can both of them together complete 80% of the work...