Question
‘Neha’ can complete a task in 90 days. She worked for
54 days and then left. The rest of the task was completed by ‘Karan’ in 24 days. How much time would Karan take to finish 80% of the task?Solution
ATQ,
Neha’s work = 54/90 = 3/5
Remaining = 1 - 3/5 = 2/5
Karan does 2/5 in 24 days
Full work time for Karan = 24 × (5/2) = 60 days
80% work = 0.8 × 60 = 48 days
The recommended technique for planting in saline soils to improve sugarcane yields by around 15% is
Who is appointed as the chairperson of the ATMA Governing Board?
Trichoderma viride, a bioagent to control some diseases in crop plants, acts as:
The correct order of boiling point of primary (1 ˚ ), secondary (2 ˚ ) and tertiary (3 ˚ ) alcohols is
Which sheep breed of northwest India known for best quality white wool?
Which asexual fruiting body is produced by Helminthosporium?
Which amongst the following is a commonly used method for determining soil moisture constant under laboratory conditions?
The Indian Institute of Packaging (IIP) is an autonomous body set up by the leading packaging and allied industries and the Department of Commerce, Gov...
Which is true for CAP.
Seed dormancy due to hard seed coats can be broken by: