Question
‘Neha’ can complete a task in 90 days. She worked for
54 days and then left. The rest of the task was completed by ‘Karan’ in 24 days. How much time would Karan take to finish 80% of the task?Solution
ATQ,
Neha’s work = 54/90 = 3/5
Remaining = 1 - 3/5 = 2/5
Karan does 2/5 in 24 days
Full work time for Karan = 24 × (5/2) = 60 days
80% work = 0.8 × 60 = 48 days
Select the most appropriate option to fill in the blank.
We ________Rohit for the last two months.
They chanted slogans praising their beleaguer leader who, along with his younger brother, is the target of anti-government protests in the island that i...
Alter
Amid allegations (A) of corruption, compromises (B) on safety and other issues, some of the key officials in the team were shifted out to insufficient ...
Time perception raises a number of ______ puzzles, including what it means to say we perceive time.
Select the most appropriate synonym of the given word.
PERSIST
Select the most appropriate ANTONYM of the given word.
DILUTE
Select the most appropriate antonym of the given word.
RELEVANT
Select the most appropriate option to substitute the underlined segment in the given sentence. If no substitution is required, select ‘No substitutio...
Select the most appropriate option to substitute the underlined segment in the given sentence. If there is no need to substitute it, select ‘No substi...