      ‘Neha’ can complete a task in 90 days. She worked for

      54 days and then left. The rest of the task was completed by ‘Karan’ in 24 days. How much time would Karan take to finish 80% of the task?
      A 38 days Correct Answer Incorrect Answer
      B 48 days Correct Answer Incorrect Answer
      C 36 days Correct Answer Incorrect Answer
      D 24 days Correct Answer Incorrect Answer

      Solution

      ATQ,

      Neha’s work = 54/90 = 3/5

      Remaining = 1 - 3/5 = 2/5

      Karan does 2/5 in 24 days

      Full work time for Karan = 24 × (5/2) = 60 days

      80% work = 0.8 × 60 = 48 days