Question
‘Neha’ can complete a task in 90 days. She worked for
54 days and then left. The rest of the task was completed by ‘Karan’ in 24 days. How much time would Karan take to finish 80% of the task?Solution
ATQ,
Neha’s work = 54/90 = 3/5
Remaining = 1 - 3/5 = 2/5
Karan does 2/5 in 24 days
Full work time for Karan = 24 × (5/2) = 60 days
80% work = 0.8 × 60 = 48 days
Which state recently re-adopted its Prohibition of Online Gambling and Regulation of Online Games Bill, 2022?
- What is the atomic number of the element Bromine?
Who is the founder and CEO of the messaging app Telegram?
- Who established the Dipasikha Dance Foundation in Chennai in 1984?
- In which district is the Baira Siul Dam located?
What does the ozone layer protect the Earth from?
- Who referred to Article 356 of the Indian Constitution as a "dead letter"?
Assertion (A): Cities generate about 66% of India's GDP and 90% of government income.
Reason (R): Urban local bodies (ULBs) receive less than 1% ...
India signed an agreement for LNG infrastructure and power development with which country?
- Which Indian state has recorded a 20% increase in cotton sowing recently?