A takes 24 hours more than B to complete the work, and
32 hours more than C to complete the same work. The combined time taken by A and B to finish the work is equal to the time taken by C alone. Find the time required by B alone to complete the work.Solution
ATQ,
Let the time taken by C alone to complete the work be ‘x’ days. So, time taken by A alone to complete the work = (x + 32) days. Time taken by B alone to complete the work = (x + 32 – 24)= (x + 8) days According to question, {(x + 32) (x + 8)}/ {(x + 32) + (x + 8)} = x x ² + 40x + 256 = x(2x + 40) x ² = 256 x = 16 So, time taken by B alone to complete the work = 16 + 8 = 24 daysÂ
How many types of the amendment are mentioned by the Indian Constitution as per Article 368?
Which Union Territory (UT) has become the first to implement the PM Vishwakarma Yojana (PMVY)?
The Iron Age in North India is archaeologically represented by assemblages that mainly contain which of the following particular pottery types?
L...
Which state/union territory secured 2nd place in the 38th National Games 2025 held in Uttarakhand?
________ Language is also called programming language.
The difference between the value of exports and the value of imports of goods of a country in a given period of time is called _______.
‘Midnight’s Children’ is a novel by which of the following writers?
The Sustainable Development Goals (SDG) performance index measures the performance of how many countries?
Which of the following statements is correct regarding badminton?Â
I. At the beginning of the game of badminton and when the score is even, the ...
Which of the following statements is INCORRECT about the Directive Principles of State Policy?