Question

A takes 24 hours more than B to complete the work, and 32 hours more than C to complete the same work. The combined time taken by A and B to finish the work is equal to the time taken by C alone. Find the time required by B alone to complete the work.

A 30 days
B 12 days
C 24 days
D 27 days
E None of these