Question

Together, Ali and Imran take 40 days to complete a project. After working jointly for 32 days, they left, and Zara completed the remaining work in 4 days. How much time would Zara take to complete 70% of the work on her own?

A 10.8
B 32.5
C 62.5
D 28.4
E None of these