Together, Ali and Imran take 40 days to complete a project.
After working jointly for 32 days, they left, and Zara completed the remaining work in 4 days. How much time would Zara take to complete 70% of the work on her own?Solution
ATQ,
Fraction of work done by Ali and Imran = 32 / 40 = 4/5
Fraction of work done by Zara = 1 - 4/5 = 1/5
So, number of days taken by Zara alone to complete the entire work = 4 ÷ (1/5) = 20 days
So, time taken by Zara to complete 70% of the work = 20 × 0.70 = 14 days
As per the Code on wages, 2019 no employer shall pay to any employee wages _______________
The incorporation document shall consist of a statement of an advocate, CA or CS that the LLP has complied with all the provisions of LLP act, person ma...
Special leave to appeal can be granted by the Supreme Court-
Where a resolution is passed at an adjourned meeting of a company the resolution shall, for all purposes, be treated as_________________
The National Company Law Tribunal shall consist of ____________ as the Central Government may deem necessary
 What Is the full form of CIN?
The provision governing counter claim is covered under which of the following orders of CPC?
What shall be credited to the Depositor Education and Awareness Fund as laid down under the Banking Regulation Act?
Who are intermediary under the Insurance Act?
After dissolution of the firm, goodwill of the firm __.