    • Question

      The time taken by ‘X’, ‘Y’ and ‘Z’ to complete

      a task is ‘6n’ days, ‘9n’ days and ‘12n’ days, respectively. What is the ratio of their efficiencies?
      A 5:4:7 Correct Answer Incorrect Answer
      B 6:4:3 Correct Answer Incorrect Answer
      C 2:8:9 Correct Answer Incorrect Answer
      D 1:5:7 Correct Answer Incorrect Answer

      Solution

      ATQ,

      Since, efficiency is inversely proportional to time taken

      So, ratio of efficiency = (1/6n) : (1/9n) : (1/12n) = 6 : 4 : 3