A and B working together, can do a piece of work in
4(1/2) hours. B and C working together can do it in 3 hours. C and A working together can do it in 2(1/4) hours. All of them begin the work at the same time. Find how much time they will take to finish the piece of work?Solution
AB = 9/2 BC = 3 CA = 9/4 Efficiency of AB : BC : CA = 2 : 3 : 4 LCM (Total units) = 36 Now, 2(A + B + C) = 2 (2 + 3 + 4) = 18 To finish the work they will take = 36/18 = 2 hours
According to Section 178 of the Companies Act, what is the composition requirement for the Nomination and Remuneration Committee of a listed public com...
Which of the following conditions must be met for a person to be guilty of ‘attempt to murder’ under Section 109(1)?
According to Section 17 of the Limitation Act, 1963, in which circumstance will the limitation period NOT begin to run?Â
Who bears the burden of proof in a legal proceeding when establishing the existence of facts?
A promoter of a company transfers his shares to another person without proper disclosure. The transfer is questioned on the ground that it violates dis...
Within how many days must mediation be completed as per the general rule in the Act?
Which of the following does not constitute an offence under Section 152?Â
As per S.8 of the Indian Evidence Act, 1872 which of the following is covered?
As per the Insurance Act which of the following conditions would not disqualify a person from being appointed as an insurance agent?
A pharmaceutical company with 60% market share in a particular drug category refused to supply to a distributor who was also selling competitors' produ...