Question
If 15 men or 10 boys can finish a task in 18 days, how
long will it take for a team of 12 men and 15 boys to complete the same task? (Calculate approximate value)Solution
According to the question,
15M = 10B
Or, 3M = 2B
Therefore, (12M + 15B) = (8B + 15B) = 23B
10 boys take 18 days to complete the work
Therefore, time taken by 23 boys to complete the work = (10 × 18) / 23 = 7.83 days or 8 days
Which of the following cases upheld ‘secularism’ as a basic feature of the Indian Constitution even before the word ‘secular’ was inserted in th...
An injunction which can only be granted by a decree made at the hearing and upon the merits of the suit is known as _____________
 __________ is a state in which a company’s liabilities are more than its assets so that is unable to repay its debts
__________ is a state in which a company’s liabilities are more than its assets so that is unable to repay its debts
Who among the following has the power to declare what language shall be deemed to be commonly used in each district?
Anticipatory bail may be granted by
Which documents contains the regulations relating to the internal management of a company?
A statute which governs the event which takes place in future after the statute has came into existence is
When the pawnor has obtained possession of the goods pledged by him under a contract voidable but the contract under section 19 or section 19A has not b...
As per the IBC Insolvency Commencement date means___________________