Question
If 15 men or 10 boys can finish a task in 18 days, how
long will it take for a team of 12 men and 15 boys to complete the same task? (Calculate approximate value)Solution
According to the question,
15M = 10B
Or, 3M = 2B
Therefore, (12M + 15B) = (8B + 15B) = 23B
10 boys take 18 days to complete the work
Therefore, time taken by 23 boys to complete the work = (10 × 18) / 23 = 7.83 days or 8 days
In the following question, among the four answer figures which one can be formed from the cut out pieces given below?
Find out from the alternatives as how the pattern would appear when the transparent sheet is folded at the dotted line.
A paper is folded and cut as shown below. How will it appear when unfolded?
In the following question, among the four answer figures which one can be formed from the cut out pieces given below?
Choose a figure which would most closely resemble the unfolded form of Figure (Z).
Choose a figure which would most closely resemble the unfolded form of Figure (Z).
A piece of paper is folded and cut as shown below in the question figures. From the given answer figures, indicate how it will appear when opened?
...Among the four answer figures, which can be formed from the cutpieces given below?
In the following question, among the four answer figures which one can be formed from the cut out pieces given below?
In the following question, among the four answer figures which one can be formed from the cut out pieces given below?