Question
If 15 men or 10 boys can finish a task in 18 days, how
long will it take for a team of 12 men and 15 boys to complete the same task? (Calculate approximate value)Solution
According to the question,
15M = 10B
Or, 3M = 2B
Therefore, (12M + 15B) = (8B + 15B) = 23B
10 boys take 18 days to complete the work
Therefore, time taken by 23 boys to complete the work = (10 × 18) / 23 = 7.83 days or 8 days
Consider the following statements:
1.The Eighth Schedule of the Indian Constitution lists 22 languages recognized as scheduled languages of India...
Which of the following grades does the Secondary stage cover as per the Curricular and Pedagogical Structure mentioned in the National Education Policy,...
Which of the following organizations has already made a profit of Rs 18,348 crore in the second quarter of the financial year 2022?
Ullambana is the festival of which of the following religion?Â
Approximately how far away from Earth will the Aditya-L1 satellite be positioned?
Consider the following statement about NATPOLREX-IX:
1. The 9th National Level Pollution Response Exercise was conducted by the Indian Coast Guar...
Identify the cultural festival on the basis of given clues:
i) This festival brings together craftsmen like potters, embroiderers, weavers, wood ...
In August 2024, India successfully named three underwater geographical structures in the Indian Ocean: the Ashoka seamount, the Chandragupt ridge, and t...
In which sport did Meena Kumari Maisnam win the gold medal in Germany in April 2019?
Meher had two large chunks of coal. She set fire to the first chunk and broke the second one into pieces. Help Meher understand what kind of changes hap...