Question
‘X’ is 25% more efficient than ‘Y’, and ‘Z’ is 25% less efficient than ‘Y’. Together, they can complete a job in 40 days. If X and Y work together for 30 days, how long will Z take to finish the remaining work?
More Time and work Questions
- A 40 hectare field is reaped by 4 men, 6 women and 8 children together in 10 days. If working capabilities of a Man, a Woman and a Child are in the ratio 6...
- P alone can finish a piece of work ‘M’ in 6 days while Q takes 3 days to finish it alone. P, Q and R working together can finish the work ‘N’ which is 12 t...
- ‘A’ alone can complete a work in 12 days. ‘B’ alone can complete the same work in 20 days. If ‘A’ and ‘B’ work together for 6 days, then the remaining work...
- A’ and ‘B’ together can complete a work in 10 days while ‘A’ takes 18 days to complete the same work alone. If ‘C’ is 25% more efficient than ‘B’, then fin...
- Ratio of the efficiency of 'A', 'B' and 'C' is 4:5:2, respectively. 'A' and 'B' complete the work together in 20 days. Find the time taken by 'B' and 'C' t...
- 32 workers can complete a task in 18 days. They all started together, but after how many days should 12 workers quit so that the task gets completed in 27 ...
- The ratio of time taken by P, Q and R to complete work alone is 6:7:3 respectively. If all three together complete the work in 7 days, then find in how man...
- ‘P’ can complete a project in 12 days. ‘Q’ is 40% less efficient than ‘P’. Working together, ‘P’, ‘Q’ and ‘R’ can finish the job in 5 days. In how many day...
- 'A' requires 16 more days to finish a task compared to 'B'. When 'A' and 'B' collaborate, they complete the task in 9 days fewer than 'B' would need to fin...
- A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt