18 women can do piece of work in 12 days. 12 men can do
the same piece of work in 9 days. Find in how many days will 8 men and 8 women complete that work?Solution
Alternate Method: 12 Men can do this job in 9 days and 18 women can do this job in 12 days It means 6 men or 3 women can do this job in = 36 days So 8 Men and 8 women can do this job in = 36/{8/6 + 8/3} = 36/ {8/(6/3) = 9 days
Which organization has developed the Indian Light Tank (ILT)?
Who was the winner of the first Indian Premier League?
What is one - half of the wave height called?
During a game of hockey, following an offence, if a player is shown a yellow card then he will be sent off the pitch for _______.
When was Kumaon Iron Works Company established in Uttarakhand Region?
For which crop was the Champaran movement organized by Gandhiji in 1917?
Which of the following is NOT a correct match?
Which of the following constitutional amendment act empower the state government to form 3 tier local self-government?
Who among the following has won a silver medal in the javelin throw at the first World Para Athletics Junior Championships in Nottwil, Switzerland?
What is the full form of ROC in the context of global financial market regulation involving over 65 regulators and authorities from more than 50 countries?