Question
A’ and ‘B’ together can complete a work in 10 days while ‘A’ takes 18 days to complete the same work alone. If ‘C’ is 25% more efficient than ‘B’, then find the time taken by ‘C’ alone to complete the whole work.
More Time and work Questions
- ‘C’ and ‘D’ can complete a job in 20 days and 25 days respectively. They completed it together for Rs. 9,000. What will be C’s share?
- A group of 24 men is capable of finishing a task in 15 days. Initially, 12 men begin the job and work on it for 12 days. After this period, an additional '...
- A and B together, B and C together and A and C together can complete a piece of work in 40 days, 30 days and 50 days respectively. Find the ratio of the ef...
- Ayaan and Kabir started working together on a task. Ayaan does 4 units per day and Kabir can finish the full task in 25 days alone. The total work is 100 u...
- A and B can complete a task together in 16 days, while B alone takes 32 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- A and B can complete a job together in 30 days; B and C can complete the same job together in 25 days, while C and A can complete the same job together in ...
- 42 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for 42 ...
- Puneet and Qureshi together can complete (7/8)th of a piece of work in 9 days, Qureshi and Rohit together can complete (3/5)th of the work in 8 days and Pu...
- Riya completes 40% of a task in 24 days, while Siya finishes 30% of the same task in 27 days. Riya begins the task alone and stops after 30 days. How long ...
- A, B and C together can complete a project in 6 days. A and B together can complete it in 10 days, and B and C together can complete it in 12 days. In how ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)