πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    Question

    A’ and β€˜B’ together can complete a work in 20 days

    while β€˜A’ takes 30 days to complete the same work alone. If β€˜C’ is 25% more efficient than β€˜B’, then find the time taken by β€˜C’ alone to complete the whole work.
    A 45 days Correct Answer Incorrect Answer
    B 46 days Correct Answer Incorrect Answer
    C 48 days Correct Answer Incorrect Answer
    D 49 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Let the total work = 60 units Efficiency of (A + B) = 60/20 = 3 units/day Efficiency of β€˜A’ = 60/30 = 2 unit/day Therefore, efficiency of β€˜B’ = 3 – 2 = 1 units/day Efficiency of β€˜C’ = 1.25 Γ— 1 = 1.25 units/day Required time taken = 60/1.25 = 48 days

    Practice Next
    ask-question