Question
'C' can complete a work in 18 days whereas 'D' can do
the same work in 30 days.They started working together but 'C' worked with 60% of his efficiency while 'D' worked with 50% of his efficiency. Find the total time taken by them to complete the work this way.Solution
ATQ, Let the total work be 90 units (LCM of 18 and 30) So, efficiency of 'C' = (90/18) = 5 units/day And efficiency of 'D' = (90/30) = 3 units/day New efficiency of 'C' = 60% of 5 = (0.6) X 5 = 3 units/day New efficiency of 'D' = 50% of 3 = (0.5) X 3 = 1.5 units/day So, required time =(90/(3+1.5) = 90/4.5 = 20 days
The two famous writers crossed swords with each other on every issue.
My brother said to me, “Don’t waste your time.”
Wear the green willow
In each of the following questions, an idiomatic expression/a proverb has been underlined – followed by four alternatives. Choose the one which best ...
Which of the phrases given below each statement should replace the phrase printed in bold in the sentence to make it grammatically correct. If the sent...
Select the most appropriate meaning of the given idiom.
Vanish into thin air
Once in a blue moon
- Select the most appropriate option to substitute the underlined segment in the given sentence.
After months of hard work, the team finally achieved... What is correct usage of given idiom.
Break the ice
Select the most appropriate option to substitute the bold segment in the given sentence.
Because of his misbehaviour, he is bound to face the...