Question
Anil, Anshika and Anamika can do a certain piece of work in 64 days, 72 days and 96 days, respectively. All of them started working together but after ___ days, Anil and Anshika left the job and the remaining work is done by Anamika alone in ___ days. The values given in which of the following options will fill the blanks in the same order in which is it given to make the above statement true:
Anil, Anshika and Anamika can do a certain piece of work in 64 days, 72 days and 96 days, respectively. All of them started working together but after ___ days, Anil and Anshika left the job and the remaining work is done by Anamika alone in ___ days. The values given in which of the following options will fill the blanks in the same order in which is it given to make the above statement true:
I. 24, 4
II. 11, 53.5
III. 18, 27
IV. 12, 50
More Time and work Questions
- A work can be completed by ‘A’ and ‘B’, alone in 10 days and 12 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- If ‘X’ finishes a project in 24 days whereas ‘X’ and ‘Y’ working together can finish it in 15 days, then determine the time ‘Y’ alone will take to finish t...
- Ram, Ankit and Shivam together can do a piece of work in 10/3 days. Ram could do it alone in 6 days and Ankit could do it alone in 12days. In how many days...
- ‘A’ can finish a project in 40 days, whereas ‘B’ finishes 50% of the project in 12 days less than ‘A’. How many days will it take both ‘A’ and ‘B’ to compl...
- Deepak and Divya, alone can complete a work in 18 days and 27 days, respectively. They started the work together and left after 9 days such that the remain...
- A is twice as efficient as B and can finish a piece of work in 20 days less than B. B can finish this work in how many days?
- A, B, and C are hired to complete a task. A and B together can finish the work in 12 days, B and C together in 15 days, and A and C together in 20 days. Ho...
- Saurabh can complete a piece of work in 20 days. He worked for 5 days and left. Anirudh completed the remaining work in 12 days. If both of them had done t...
- A man can complete a job alone in 20 days. A woman can complete half of the same job in 15 days. If both work together, how many days will it take them to ...
- A contractor undertook to make 20 km of roadway in 48 weeks. In 28 weeks, 8 km was completed by 120 men working 12 hours a day. The men then agreed to work...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt