Question
Person A can complete a certain task in 20 days, while
person B can finish the same task in x days. Together, they can complete the task in 12 days. Determine the value of x.Solution
Let total amount of work = 60 units (LCM of 20 and 12) Efficiency of βAβ = 60/20 = 3 units/day Efficiency of βAβ and βBβ together = 60 /12 = 5 units/day Efficiency of βBβ = 5 β 3 = 2 units/day So, x = 60/2 = 30 days
Which country is set to launch Southeast Asia's first high-speed railway, a project backed by China, with a Chinese-made bullet train named "Whoosh"?
Which state has launched ‘Rakshak’ road safety initiative, under which 30,000 first responders will be trained by 300 master trainers?
RBI Innovation Hub and which of the following firm has signed a Memorandum of Understanding to give early-stage entrepreneurs with unique and disruptive...
Identify the correct statement:
1. CSIR operates under the Union Ministry of Science and Technology.
2. The President of CSIR is the Prime...
Which key topics were discussed at the World Leaders Summit 2024 held at the House of Lords in the UK Parliament?
Who led the Indian delegation during the inaugural meeting of the India-US Strategic Trade Dialogue (IUSSTD)?
Which of the following private sector finance companies has launched the initiative ‘Har Time EMI On Time'?
Which company has unveiled a new development centre in Visakhapatnam, Andhra Pradesh, aiming to bring the workplace closer to its employees and harness ...
βWorld of Advance Virtual Experience (WAVE)β is an initiative of which Indian public sector bank?
What is the expected share of India in global consumption by 2050, according to projections?