Question
Person A can complete a certain task in 20 days, while
person B can finish the same task in x days. Together, they can complete the task in 12 days. Determine the value of x.Solution
Let total amount of work = 60 units (LCM of 20 and 12) Efficiency of ‘A’ = 60/20 = 3 units/day Efficiency of ‘A’ and ‘B’ together = 60 /12 = 5 units/day Efficiency of ‘B’ = 5 – 3 = 2 units/day So, x = 60/2 = 30 days
What will happen when supply elasticity is less than demand elasticity?
Which of the following is not a test related to Heteroscedasticity?
An increase in the expected rate of inflation
Which of the following would shift the ‘Marginal Efficiency of Investment’ (MEI) schedule to the right?
Which of the following is a synonym of "Undistributed Profits"?
Why is the choice of the social discount rate crucial and often contentious in the economic analysis of long-term environmental projects (e.g....
How much additional financing did the World Bank approve to support India’s low carbon transition?
Which of the following is not an example of market failure?
Calculate Domestic Income:
Items
<...During the latest RBI Monetary Policy Committee (MPC) meeting held in August 2024, what was the decision made regarding the repo rate?
Relevant for Exams: