Question
Person A can complete a certain task in 20 days, while
person B can finish the same task in x days. Together, they can complete the task in 12 days. Determine the value of x.Solution
Let total amount of work = 60 units (LCM of 20 and 12) Efficiency of βAβ = 60/20 = 3 units/day Efficiency of βAβ and βBβ together = 60 /12 = 5 units/day Efficiency of βBβ = 5 β 3 = 2 units/day So, x = 60/2 = 30 days
What is Apache Spark primarily used for in big data processing?
Which logic gate produces an output that is the logical sum of two or more inputs?
What happens if there is insufficient memory to allocate in dynamic memory allocation?
What is the primary purpose of a firewall in network security?
State true or false
The Arithmetic Logic Unit (ALU) is a crucial component of the CPU responsible for performing arithmetic and logical operat...
What does a lexer (lexical analyzer) do in the compilation process?
What does below UNIX command do?
rm file1 file2
Which of the following is NOT a common use of PHP?
The truth table for an OR gate has an output of 1 when:
What is a "51% attack" in the context of blockchain?