Question
Person A can complete a certain task in 20 days, while
person B can finish the same task in x days. Together, they can complete the task in 12 days. Determine the value of x.Solution
Let total amount of work = 60 units (LCM of 20 and 12) Efficiency of ‘A’ = 60/20 = 3 units/day Efficiency of ‘A’ and ‘B’ together = 60 /12 = 5 units/day Efficiency of ‘B’ = 5 – 3 = 2 units/day So, x = 60/2 = 30 days
Which of the following points are ‘correct’ with respect to the Pradhan Mantri Suraksha Bima Yojana?
I) The Pradhan Mantri Suraksha Bima Yoja...
Finance Minister announced in Union Budget 2024 speech, interest subsidy in terms of e-voucher will be given to 1 lakh students availing loans up to:
Which of the following Ministry if implementing the KRISHI UDAN Scheme?
What does the Gujarat Declaration emphasize regarding the application of traditional, complementary, and integrative medicine (TCIM)?
Which of the following schemes has been approved by the Government of India to support research and development in the textile sector?
Pradhan Mantri Shram Yogi Maan-dhan (PM-SYM) is a Central Sector Scheme administered by the Ministry of Labour and Employment and implemented through _...
_____ has been decided as the International Year of Millets.
What is the primary impact of persistent inflation on an economy?
Under the MSME credit enhancement scheme, the guarantee cover has been increased from ₹5 crore to—
_________ is the first country with which cross border Person to Person (P2P) payment facility has been launched.