πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      There were 25 workers to complete a job in 10 days. But

      after 4 days, 10 workers were reassigned. How many more days will be needed now?
      A 5 days Correct Answer Incorrect Answer
      B 4 days Correct Answer Incorrect Answer
      C 3 days Correct Answer Incorrect Answer
      D 7 days Correct Answer Incorrect Answer

      Solution

      ATQ,

      Assume efficiency of each worker = 'e' units/day

      Total work = 25 Γ— 10 Γ— e = 250e units

      Work completed in 4 days = 25 Γ— 4 Γ— e = 100e units

      Work remaining = 250e - 100e = 150e units

      Remaining workers = 25 - 10 = 15

      Time needed = 150e Γ· (15 Γ— e) = 10 days

      Extra days = 10 - 6 = 4 days

      Practice Next
      ask-question