Question
‘P’ can finish a task in 36 days, while ‘Q’ can
do the same task in (x + 4) days. If both work together and finish the task in 12 days, what is the value of (2x + 9)?Solution
Let total work be 36(x + 4) units Efficiency of P = 36(x + 4) ÷ 36 = (x + 4) units/day Efficiency of Q = 36(x + 4) ÷ (x + 4) = 36 units/day Now, (x + 4 + 36) × 12 = 36(x + 4) 12x + 480 = 36x + 144 24x = 336 x = 14 Required value = 2x + 9 = 2×14 + 9 = 37
Who among the following was the recipient of the Infosys Prize 2019 for Humanities?
‘Abhilekh Patal’ is related to
A school has 100 students and every student plays either cricket or football or both. The number of students who play cricket is twice the number of st...
In which of the following cities is the ‘Raja Bhoj’ airport located?
What is the minimum pension provided under the NPS Vatsalya scheme?
The GeM SAHAY platform is designed to be 'lender agnostic,' meaning:
What is the main advantage that ABC Corporation has derived from adopting accounting standards?
What is the index of the Bombay Stock Exchange (BSE) known as?
Airbnb will invest $100mn inIndian hotel startup OYO. . Airbnb deals in Which service ?
HDFC bank limited launched which of the following campaign to create awareness on cyber frauds? Â