Question
βPβ can finish a task in 36 days, while βQβ can
do the same task in (x + 4) days. If both work together and finish the task in 12 days, what is the value of (2x + 9)?Solution
Let total work be 36(x + 4) units Efficiency of P = 36(x + 4) Γ· 36 = (x + 4) units/day Efficiency of Q = 36(x + 4) Γ· (x + 4) = 36 units/day Now, (x + 4 + 36) Γ 12 = 36(x + 4) 12x + 480 = 36x + 144 24x = 336 x = 14 Required value = 2x + 9 = 2Γ14 + 9 = 37
Who formed the Indian Railways Association to introduce the railway in India?
The Konkan Railway was formed in the year:
The headquarters of Southern Coast Railway is located in _____________________
The first passenger train service in the south of India began in the year
Which railway station became the country's first all-women railway station under non- suburban category?
Who is the sole customer of DFCCIL?
Jamalpur has a training institute of Indian Railways for the training of
Deccan Odyssey is run by which state rail tourism?
Which is the Longest train in India?
A platform surrounded by rail lines from all the four sides is known as ________________ ?