Question
βPβ can finish a task in 36 days, while βQβ can
do the same task in (x + 4) days. If both work together and finish the task in 12 days, what is the value of (2x + 9)?Solution
Let total work be 36(x + 4) units Efficiency of P = 36(x + 4) Γ· 36 = (x + 4) units/day Efficiency of Q = 36(x + 4) Γ· (x + 4) = 36 units/day Now, (x + 4 + 36) Γ 12 = 36(x + 4) 12x + 480 = 36x + 144 24x = 336 x = 14 Required value = 2x + 9 = 2Γ14 + 9 = 37
Mughal Zagir means
On which river's bank is the archaeological site Harappa located?
Which among the following was founded by Gopal Krishna Gokhale?
During which period did the Maurya Empire exist?
‘Dibrugarh’ is situated on the bank on the river _________
Recently, the Government of India gave the approval to administer Remdesivir for emergency use in patients suffering from COVID-19. In this context, con...
From which space agency was the spacecraft "Psyche" launched?
During Mihira Bhoja's reign, the ancient city of Kannauj was known by which name?
Who was the original builder of Jantar Mantar in New Delhi?
What is the name given to the land given as a gift to the temples of Chola Dynasty?