Question
‘P’ can finish a task in 36 days, while ‘Q’ can
do the same task in (x + 4) days. If both work together and finish the task in 12 days, what is the value of (2x + 9)?Solution
Let total work be 36(x + 4) units Efficiency of P = 36(x + 4) ÷ 36 = (x + 4) units/day Efficiency of Q = 36(x + 4) ÷ (x + 4) = 36 units/day Now, (x + 4 + 36) × 12 = 36(x + 4) 12x + 480 = 36x + 144 24x = 336 x = 14 Required value = 2x + 9 = 2×14 + 9 = 37
When was the World Bank established?
Which bank has become the first to officially introduce the Mahila Samman Savings Certificate (MSSC) scheme?Â
Where did the 36th National Games take place in September – October 2022?
Which type of banks are allowed to participate in government related business?
Which one of the following is provided under the Third Schedule of the Factories Act, 1948?
Which of the following personalities was conferred with the ‘Padma Vibhushan’ award?Â
Business, commerce and movement within India are described as part of the Constitution?
______ drains into Arabian sea.
In a volleyball game, each team comprise of how many players?
 To reduce a bank’s risks on confirmations and negotiations of irrevocable letters is called?