      Question

      Sita is 50% more efficient than Simran. Working

      together, they finish the work in 24 days. How long will Sita take to complete the work alone?
      A 28 days Correct Answer Incorrect Answer
      B 40 days Correct Answer Incorrect Answer
      C 12 days Correct Answer Incorrect Answer
      D 32 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the efficiency of Simran be '4e' units/day. Efficiency of Sita = 1.5 × 4e = '6e' units/day. Total work = (4e + 6e) × 24 = '240e' units. Required time = (240e / 6e) = 40 days.