Question
A and B together can finish a work in 10 days. If A alone can finish it in 25 days, in how many days can B alone finish it?
Solution
Let total work = 1 unit. (A + B)βs 1-day work = 1/10 Aβs 1-day work = 1/25 So Bβs 1-day work = 1/10 β 1/25 LCM(10,25) = 50 1/10 = 5/50 1/25 = 2/50 Bβs 1-day work = (5 β 2)/50 = 3/50 Time for B alone = 1 Γ· (3/50) = 50/3 days
More Time and work Questions
- Anupam requires 30% more time than Aman to complete a certain task. If both of them work together and earn a total of Rs. 23,000, determine Anupam's share ...
- A can do a job alone in 66 days, B can do it alone in 55 days, while A, B, and C working together can complete the job in 11 days. In how many days can C d...
- A can complete a task in 20 days, and B can complete it in 25 days. When B and C collaborate, they can finish the same task in 75/8 days. Now, if A and C i...
- A can complete a work in 15 days and B can complete the same work in 20 days. They work together for 5 days. If after that B's efficiency increases by 25%,...
- Anupam can do a piece of work in 36 days and Rajveer can do it in 15 days. Diksha can do the same work in (17/18) times the number of days required by both...
- Two pipes X and Z can fill a tank in 36 hours and 48 hours respectively, while pipe Y can drain the tank in 72 hours. If pipes X and Z are opened together ...
- A, B and C can complete a work in 15, 20 and 30 days respectively. They all start working together. After 3 days, C leaves. The remaining work is completed...
- Anil and Ashish receive Rs.2000 for work of 8 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
- A and B individually can complete the work in 20 days and 30 days respectively. If the time taken by C alone to complete the work is 1.25 times the time ta...
- Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' and...