Question
"Amit" and "Bhanu" have respective completion times of
20 and 30 days for a task. They began working together on the project, but after a few days, "Amit" left and "Chintu," who can finish the entire task on her own in ten days, joined. Four days before the job was finished, "Chintu" left. Determine the amount of work completed by "Bhanu" if "Amit" and "Chintu" worked for a similar number of days.ÂSolution
ATQ, Let the total work = 60 units (L.C.M of 20, 30 and 10) Therefore, efficiency of ‘Amit’ = 60/20 = 3 units/day Efficiency of ‘Bhanu’ = 60/30 = 2 units/day Efficiency of ‘Chintu’ = 60/10 = 6 units/day Let ‘Amit’ and ‘Chintu’ worked for ‘d’ days According to the question, 5d + 8d + 4 × 2 = 60 13d = 52 Or, d = 4 Therefore, work will get completed in d + d + 4 = 12 days Therefore, work done by ‘Bhanu’ = 12 × 2 = 24 units Required ratio = 24/60 = 2/5
National pest of india is
This leg type is observed in insects like the praying mantis, featuring spiny femurs and tibiae that interlock to form a gripping mechanism
Drones are
Which of the following structures is not the part of the insect’s head capsule?Â
The type of antennae found in Honeybee are………………
Which pest is identified by the ‘honeydew’ it secretes, which often leads to the development of sooty mold on plant leaves ?
Chili leaf curl disease is spread by vector_________
Which of the following pair is not correct?
Which mechanism of resistance involves adverse effects on the biology of insects and their progeny due to biochemical and biophysical factors in the hos...
Trichogramma japonicum is a natural parasitoid which is used to control ________