Question
"Amit" and "Bhanu" have respective completion times of
20 and 30 days for a task. They began working together on the project, but after a few days, "Amit" left and "Chintu," who can finish the entire task on her own in ten days, joined. Four days before the job was finished, "Chintu" left. Determine the amount of work completed by "Bhanu" if "Amit" and "Chintu" worked for a similar number of days.ÂSolution
ATQ, Let the total work = 60 units (L.C.M of 20, 30 and 10) Therefore, efficiency of ‘Amit’ = 60/20 = 3 units/day Efficiency of ‘Bhanu’ = 60/30 = 2 units/day Efficiency of ‘Chintu’ = 60/10 = 6 units/day Let ‘Amit’ and ‘Chintu’ worked for ‘d’ days According to the question, 5d + 8d + 4 × 2 = 60 13d = 52 Or, d = 4 Therefore, work will get completed in d + d + 4 = 12 days Therefore, work done by ‘Bhanu’ = 12 × 2 = 24 units Required ratio = 24/60 = 2/5
Which of the following combination is incorrect?
Which can help a producer in determining how much of a product is required to be produced?
Corrugation method of irrigation is suitable for
The highest category of soil nomenclature is called as
Pre emergence herbicides are applied by
Phosphorus uptake in alkali soil is in the form of _____
Which one of the following statements is INCORRECT with respect to mass spectrometry?
Rotation involving Stylosanthus hamata & Sorghum is an example of
Installing 10-12 blue/yellow sticky traps per hectare is effective to manage: -
Which entomopathogens fungus role as biological control agent in cotton bollworm?