Question
A alone can complete a piece of work in 12 days and B alone can complete the same work in 18 days. If they work together for 4 days, then A leaves and B continues alone to finish the remaining work, in how many total days (from the beginning) will the work be completed?
More Time and work Questions
- P and Q together can complete 75% of a work in 15 days while Q alone takes 40% more time than P and Q together to complete the whole work. Find the time ta...
- The efficiency of A is half than that of B and C together. The ratio of the efficiency of B and C is 5 : 4. A, B and C together can do this work in 12 days...
- P’s 5 days work is equal to Q’s 6 days work. If P and Q together can complete the work in 25 days then how much time Q will take to complete 80% of the wor...
- Four boys and nine girls can complete a task in 24 days. Three boys and five girls can finish the same task in 36 days. How many days will it take for six ...
- A work can be completed by ‘A’ and ‘B’, alone in 18 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- A can complete a work in 24 days and B can complete the same work in 36 days. They work together for 8 days, after which A leaves. In how many more days wi...
- A alone can complete a piece of work in 12 days and B alone can complete it in 18 days. If they work together, in how many days will they complete the work...
- If 20 men or 12 boys can complete a job in 25 days, how long will it take for a team of 15 men and 18 boys to complete the same job? (Calculate approximate...
- Efficiency of a man is 25% more than that of a woman. (n + 4) men working 8 hours a day can complete a task in 20 days, whereas (2n - 4) women working 6 ho...
- 'K' and 'L' together can complete a work in 24 days. They started working together but after 16 days, 'L' left and remaining work was completed by 'K' alon...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)