Question
A alone can complete a piece of work in 12 days and B alone can complete the same work in 18 days. If they work together for 4 days, then A leaves and B continues alone to finish the remaining work, in how many total days (from the beginning) will the work be completed?
More Time and work Questions
- A can do a work in 10 days and B in 15 days. If they work on it together for 4 days then in how many days the remaining work will be completed by B?
- Pawan, Bittu, and Raju can individually complete a task in 36 days, 60 days, and 30 days, respectively. They all begin working together, but Raju stops aft...
- Amisha is 50% more efficient than Khushi. Amisha started a work, worked for 'w' days and then Khushi replaced Amisha. khushi completed the remaining work i...
- Sarthak can fill a pit of sand in 14 days while Vivaan takes 35 days to fill it. Ali can empty a full sand pit in 12 days. If all start working together in...
- The day efficiency of Rajeev is equal to the one-day efficiency of Divya and Vivek together. Divya is 25% more efficient than Vivek and starts with 20% mor...
- 'N' men can complete a work together in 25 days. All of them started the work together, but each day, two men left the work. The total time taken to comple...
- 'Ramesh' can complete a work in 40 days. He started the work and left after 24 days from starting. The remaining work was done by 'Suresh' in 30 days. Find...
- ‘A’ can do a piece of work in 15 days. ‘B’ can do 70% of the same work in 20 days. If they work together for the entire time and ge...
- Vijay can do a piece of work in 32 days and Sanjay can do the same work in 48 days. If Vijay works for 2 days and got Rs. 960, and the remaining work will ...
- A is half as efficient as B. C does half as much work as A and B together. If c alone can do the work in 40 days. Then in how many days will A, B and C tog...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt