📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!


    Question

    'P' and 'Q' can complete a task in 36 days together. If

    'P' alone can do it in 60 days, how long would 'Q' take to finish the task alone?
    A 90 days Correct Answer Incorrect Answer
    B 75 days Correct Answer Incorrect Answer
    C 65 days Correct Answer Incorrect Answer
    D 45 days Correct Answer Incorrect Answer

    Solution

    ATQ,

    Let the total work be 180 units. {LCM (36 and 60)} So, combined efficiency of 'P' and 'Q' = 180 ÷ 36 = 5 units/day Efficiency of 'P' = 180 ÷ 60 = 3 units/day So, efficiency of 'Q' = 5 - 3 = 2 units/day So, time taken by 'Q' to do the work alone = 180 ÷ 2 = 90 days

    Practice Next
    ask-question

    Not sure which exam is best for you Talk to our expert

    Get My Free Call