Question
Arjun and Karan can do a work separately in 20 days and 50 days respectively. Arjun started the work and was later joined by Karan. When should Karan join so that the total work completes in 16 days?
More Time and work Questions
- I and J together complete a piece of work in 20 days. If I alone can do it in 50 days, how many days will J alone take?
- N workers can complete a piece of work in 50 days. When 5 more workers joined, then the work got completed in 40 days, then what is the value of N?
- ‘n’ men working 12 hours a day can complete a work in 15 days while (3n – 8) men working 12 hours a day can complete the same work in 9 days. In how many d...
- Mohan, Sohan, and Rohan alone can finish a piece of work in 50, 100, and 150 days respectively. They start the work together, but Mohan leaves after 8 days...
- A, B, and C can complete a job in 15, 20, and 30 days, respectively. They start the work together but after 3 days, A leaves. Then, B works alone for 5 day...
- R and S take 10 days and 15 days respectively to complete a task alone. If they alternate work every day starting with R, how much time will it take to fin...
- A, B, and C can finish a job in 12, 15, and 18 days, respectively. They collaborate to complete the task and receive a combined payment of Rs. 592 for thei...
- A can finish a piece of work in 15 days and B can finish it in 20 days. They work together for 4 days and then B leaves. In how many more days can A alone ...
- Ishita is 0.5 times more efficient than Evita. If both of them work on alternate days starting with Ishita, they can finish the work in 19 days. If Somil a...
- A and B together can complete a piece of work in 30 days while A alone can complete 50% of the work in 25 days. Find the time taken by B to complete 20% of...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt