Question
40 men can complete a piece of work in 24 days. All of
them started the work together, after 6 days how much more men will be required to complete the same work 6 days before the schedule time.Solution
ATQ,
Total amount of work = 40 × 24 = 960 units Amount of work done by 40 men in 6 days = 40 × 6 = 240 units Let ‘x’ more men are required So, (40 + x) × 12 = 720 Or, x + 40 = 60 Or, x = 20
In a year-end examination, 6 papers-Maths, Physics, Geography, Economics, Chemistry, History- are scheduled on 6 consecutive days of a week (Monday - Sa...
FLLC is related to HNNE in a certain way based on the English alphabetical order. In the same way, AFFW is related to CHHY. To which of the following is...
In a certain code language, 'your attention please' is written as 'puw cuw zuw', 'kind attention' is written as 'muw zuw', and 'please pay attention' is...
Select the option that will replace the question mark (?) in the following figure series.
Select the Venn diagram that best represents the relationship between the following classes.
Parallelogram, Rhombus, Square, Trapezoid
Seven members A, B, C, D, E, F and G of a certain department, have a function to attend on a different day of a week, starting from Monday to Sunday of ...
In a row of people all facing north, Prince is 5th from the right end. Amit is 15th from the right end. Amit is exactly between Prince and Aditya. If Ad...
Which of the following terms will replace the question mark (?) in the given series?
MFT, NIS, PLQ, SON, WRJ, ?
Select the correct mirror image of the given figure when the mirror is placed at MN.
In the following question, select the figure which can be placed at the sign of question mark (?) from the given alternatives.