40 men can complete a piece of work in 24 days. All of
them started the work together, after 6 days how much more men will be required to complete the same work 6 days before the schedule time.Solution
ATQ,
Total amount of work = 40 × 24 = 960 units Amount of work done by 40 men in 6 days = 40 × 6 = 240 units Let ‘x’ more men are required So, (40 + x) × 12 = 720 Or, x + 40 = 60 Or, x = 20
Given below are two statements, one is labelled as Assertion (A) and the other as Reason (R):
Assertion (A): Monetary policy has an indirect effe...
Which of the following statement is/are incorrect about “Gross Domestic Product”?
I. Gross Domestic Product (GDP) is that i...
In which type of employment, the marginal productivity of labour is zero?
"ILO Conference No. 87" sometimes seen in the news is related to which of the following?
In an economy, head count ratio is the measure of:
...
Which of the following provisions are correct in regards to the State Reorganisation Act, 1956?
-
It nullif...
-
Market imperfections of a country are reflected in___________.
Which among the following represents the effective monetary policy transmission?
...The Indian economy can be most appropriately described as a ______ economy.
Which Author has been selected for Saraswati Samman 2022?