      40 men can complete a piece of work in 24 days. All of

      them started the work together, after 6 days how much more men will be required to complete the same work 6 days before the schedule time.
      A 20 days Correct Answer Incorrect Answer
      B 15 days Correct Answer Incorrect Answer
      C 25 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ,

      Total amount of work = 40 Γ— 24 = 960 units Amount of work done by 40 men in 6 days = 40 Γ— 6 = 240 units Let β€˜x’ more men are required So, (40 + x) Γ— 12 = 720 Or, x + 40 = 60 Or, x = 20