Question
40 men can complete a piece of work in 24 days. All of them started the work together, after 6 days how much more men will be required to complete the same work 6 days before the schedule time.
More Time and work Questions
- A ranch has 70 horses, and there’s food to last for 6 days. If 14 more horses are added, then how many days will the food last?
- A and B can complete a task together in 12 days, while B alone takes 24 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- M, N and O can complete a task in ‘t’, 100, and ‘t + 20’ days respectively. All three started together, but after 15 days, N dropped out. Then, 30 days bef...
- Arjun, Binny, and Chiku can collaborate to finish a particular task in 12 days. Additionally, Arjun and Binny working together can complete the task in 15 ...
- 'N' men can complete a work together in 25 days. All of them started the work together, but each day, two men left the work. The total time taken to comple...
- A, B and C can complete a work in 10, 20 and 15 days respectively. A left the work 3 days before the work was completed and B left 1 days after A had left....
- Anupam requires 30% more time than Aman to complete a certain task. If both of them work together and earn a total of Rs. 23,000, determine Anupam's share ...
- A alone can complete a work in 18 days and B alone can complete it in 27 days. They work together for 6 days and then B leaves. In how many more days will ...
- A work can be completed by ‘A’ and ‘B’, alone in 20 days and 10 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
- Pipe A alone can fill 75% of a cistern in 18 minutes. When both Pipe A and Pipe B are opened together, they can fill the entire cistern in 33 minutes. How ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)