Question
βAβ and βBβ can complete a certain work in 16
days and 32 days, respectively. They started working together and worked till completion of the work for which they got Rs. 15000 as wage. Find the share of βBβ out of total wage.Solution
Let total work = 32 units {LCM of (16 and 32)} Efficiency of βAβ = 32/16 = 2 units/day Efficiency of βBβ = 32/32 = 1 units/day Wages received by βAβ and βBβ will directly proportion to their efficiency. So share of βBβ = 15000 Γ (1/3) = Rs 5000
Alkalization also called:
Sodium adsorption ratio is a measure of the amount of sodium (Na) relative to calcium (Ca) and magnesium (Mg) in the water extract. Which of the followi...
Which among the following can be classified as often cross pollinated species?
Pradhan Mantri Fasal Bima Yojana (PMFBY) was launched in the year?Β
What plant hormone is responsible for preventing premature fruit drop in certain fruit trees like apple and cherry?
Which amendment deals with urban local governance, similar to the 73rd amendment for rural areas?
For the farmers, β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦β¦. Soil structure is favourable for plant growth.
...Name the buffalo Breed which is Blackish copper to light copper in color and have highest % of fat in milk?Β
Fanging is related to
What is the term for the process of converting atmospheric nitrogen gas into a form that plants can absorb?